Skip to main content

Main navigation

  • About ESS
    • The ESS Mandate
      • The ESS Story
    • ESS Organisation
      • Governance
        • Council Meetings
      • Committees
    • News & Press
      • Media Bank
      • Web Articles
    • Publications
    • Legal
      • ESS Privacy and Cookies Policies
    • Contact ESS
  • Science & Instruments
    • Science Using Neutrons
      • Chemistry of Materials, Magnetic & Electronic Phenomena
      • Engineering Materials, Geosciences, Archeology & Heritage Conservation and Fast Neutron Applications
      • Life Science & Soft Condensed Matter
      • Particle Physics
      • Future Science: What will we see at ESS?
        • Safer, lighter and stronger engineering materials
        • Fine-tuning 3D printing for space exploration
        • New tools in the fight against air pollution and global warming
        • Exploring the powerhouse of life
        • Better superconductors to improve cancer diagnosis
        • Bringing the most effective cancer drugs to market sooner
        • Lighting the way to next generation solar energy
        • New battery materials for a renewable energy future
        • Delivering on the Promise of Big Data
        • Putting a finger on the disorder essential to life
        • Unlocking the secrets of water
    • Instruments
      • BEER
      • BIFROST
      • CSPEC
      • DREAM
      • ESTIA
      • FREIA
      • HEIMDAL
      • LOKI
      • MAGIC
      • MIRACLES
      • NMX
      • ODIN
      • SKADI
      • T-REX
      • VESPA
    • Data Management & Software Centre
      • Computing Centre
    • Labs and Sample Environment
      • PREMP
      • FLUCO
      • TEFI
      • DEMAX
      • SULF
      • MESI
    • Committees
    • For Users
    • ESS Scientists
    • Science Events
    • Highlights of Published Papers
  • Technology
    • Accelerator
      • How It Works
      • LINAC
      • Beam Physics & Beam Diagnostics
      • Cryogenics
      • Vacuum
      • Radio Frequency Systems
      • Accelerator Test Stands
    • Target
      • How the Target works
    • Controls
  • Building ESS
    • The Building Project
      • Site, Architecture & Sustainability
      • Licensing & Planning
      • Radiation Protection & Safety
    • Progress reports from the ESS site
    • Aerial Views
  • Partnerships
    • In-Kind Contributions
    • Doing business with ESS
      • Supplier Information
      • Procurement Listings
      • Contract Award Notices
    • Grants
      • ESS in the HALRIC Project
  • Careers
    • Vacancies
    • Living & Working in Scandinavia
      • In Sweden
      • In Denmark
    • ESS Family Support
Webmail
ESS Inside
  • About ESS
    The ESS Mandate ESS Organisation News & Press Publications Legal Contact ESS
  • Science & Instruments
    Science Using Neutrons Instruments Data Management & Software Centre Labs and Sample Environment Committees For Users ESS Scientists Science Events Highlights of Published Papers
  • Technology
    Accelerator Target Controls
  • Building ESS
    The Building Project Progress reports from the ESS site Aerial Views
  • Partnerships
    In-Kind Contributions Doing business with ESS Grants
  • Careers
    Vacancies Living & Working in Scandinavia ESS Family Support

Secondary navigation

  • Publications Portal
  • Contact
  • Press
  • Behind ESS
Home

Main navigation

  • About ESS
    ess long pulse slide
    The ESS Mandate
    organisation
    ESS Organisation
    News and Press
    News & Press
    alt
    Publications
    legal and ip
    Legal
    contact ess
    Contact ESS
  • Science & Instruments
    Science using neutrons
    Science Using Neutrons
    instruments
    Instruments
    dmsc
    Data Management & Software Centre
    sss magnet
    Labs and Sample Environment
    Inauguration
    Committees
    Lab Kat
    For Users
    Scientist at work
    ESS Scientists
    diffraction
    Science Events
    Science papers image
    Highlights of Published Papers
  • Technology
    ess accelerator
    Accelerator
    target monolith
    Target
    ess ics
    Controls
  • Building ESS
    Building project
    The Building Project
    weekly construction updates
    Progress reports from the ESS site
    ess aerial snow
    Aerial Views
  • Partnerships
    tartu pump probe
    In-Kind Contributions
    procurement
    Doing business with ESS
    partner day
    Grants
  • Careers
    careers
    Vacancies
    scandinavia
    Living & Working in Scandinavia
    family
    ESS Family Support

18 November 2019

Target

More concrete has been added to the scope of the Dog Leg cover, meaning these works are now scheduled for completion in January 2020. In the A2T (Accelerator to Target), steel and precast is ongoing. In the Monolith/Utility high bay, welding of the crane beam and sandwich panel installation has started. The temporary crane will be installed early 2020, to enable ESS Target Division to lower the target vessel (2 x 30-tonne lifts). This vessel is the container and outer shielding for the Target Monolith, which will house the target's tungsten wheel.

ESS have gained parallel access to the Active Cell area to perform ceiling works in the maintenance and process cells. This involves framework, steel plates, anchor plates, penetrations and welding of the steel plates. A total of 51 concrete foundations have completed in order for equipment to go into the Utility building. Superstructure has also started for the Active Cell high bay, and steel pillars are already being put into place for one of the lab buildings.Pre-cast walls are ongoing for the Target Entrance Building.

The two lab buildings adjacent to the large Experiment Hall will be subject to Sectional Handover Inspection (SHIN) this week. This is carried out prior to handover to ESS and includes all disciplines in the building together with all the required test and system commissioning. Sectional handovers of two of the labs are scheduled for December.

Accelerator

After testing off-site at ESS Test Stand 3 and the RATS lab, the first Linac Warm Units (LWUs) have now arrived in the Accelerator tunnel. LWUs are components containing magnets and vacuum chambers and beam pipe. The units will sit in-between the cryomodules and in the beam transport area leading up to the Dog Leg.

The two lab buildings adjacent to the large Experimental Hall will be subject to Sectional Handover Inspection (SHIN) this week. This is carried out prior to handover to ESS and includes all disciplines in the building together with all the required test and system commissioning. Sectional handovers of two of the labs are scheduled for December.

FYI

Modulators are a key component at ESS, with the purpose of converting the power fed from the electrical grid to a pulse power suitable for klystrons, i.e. a reliable, constant and even electrical current. The 33 modulators at ESS have been designed in-house by the ESS Power Converters team. They have team been developed over the last few years, and the final design concept, offering a more compact, cheaper and more powerful solution, is now subject to serial production by in-kind partner ESS Bilbao in Spain. Three modulators are already being tested inside Test Stand 3 of the Klystron Gallery. The first modulator to be moved to its permanent position will be placed in the Gallery Building by the radio frequency (RF) cell, connecting to the Radio Frequency Quadrupole down in the tunnel: this is scheduled for the first quarter of 2020. Typically, there will be two ESS modulators in each RF cell powering eight klystrons, which provide the RF power for the Linac via the waveguides in the tunnel to the Gallery Building stubs.

General

In the Waste Building, the very last base slab was cast last week, and this week will see the first 8.8m high wall equipped with concrete.

Completion of the area outside the experimental buildings is ongoing. Final levelling and the laying of kerb stones and asphalt is in progress and will be completed next week.