Skip to main content

Main navigation

  • About ESS
    • The ESS Mandate
      • The ESS Story
    • ESS Organisation
      • Governance
        • Council Meetings
      • Committees
    • News & Press
      • Media Bank
      • Web Articles
    • Publications
    • Legal
      • ESS Privacy and Cookies Policies
    • Contact ESS
  • Science & Instruments
    • Science Using Neutrons
      • Chemistry of Materials, Magnetic & Electronic Phenomena
      • Engineering Materials, Geosciences, Archeology & Heritage Conservation and Fast Neutron Applications
      • Life Science & Soft Condensed Matter
      • Particle Physics
      • Future Science: What will we see at ESS?
        • Safer, lighter and stronger engineering materials
        • Fine-tuning 3D printing for space exploration
        • New tools in the fight against air pollution and global warming
        • Exploring the powerhouse of life
        • Better superconductors to improve cancer diagnosis
        • Bringing the most effective cancer drugs to market sooner
        • Lighting the way to next generation solar energy
        • New battery materials for a renewable energy future
        • Delivering on the Promise of Big Data
        • Putting a finger on the disorder essential to life
        • Unlocking the secrets of water
    • Instruments
      • BEER
      • BIFROST
      • CSPEC
      • DREAM
      • ESTIA
      • FREIA
      • HEIMDAL
      • LOKI
      • MAGIC
      • MIRACLES
      • NMX
      • ODIN
      • SKADI
      • T-REX
      • VESPA
    • Data Management & Software Centre
      • Computing Centre
    • Labs and Sample Environment
      • PREMP
      • FLUCO
      • TEFI
      • DEMAX
      • SULF
      • MESI
    • Committees
    • For Users
    • ESS Scientists
    • Science Events
    • Highlights of Published Papers
  • Technology
    • Accelerator
      • How It Works
      • LINAC
      • Beam Physics & Beam Diagnostics
      • Cryogenics
      • Vacuum
      • Radio Frequency Systems
      • Accelerator Test Stands
    • Target
      • How the Target works
    • Controls
  • Building ESS
    • The Building Project
      • Site, Architecture & Sustainability
      • Licensing & Planning
      • Radiation Protection & Safety
    • Progress reports from the ESS site
    • Aerial Views
  • Partnerships
    • In-Kind Contributions
    • Doing business with ESS
      • Supplier Information
      • Procurement Listings
      • Contract Award Notices
    • Grants
      • ESS in the HALRIC Project
  • Careers
    • Vacancies
    • Living & Working in Scandinavia
      • In Sweden
      • In Denmark
    • ESS Family Support
Webmail
ESS Inside
  • About ESS
    The ESS Mandate ESS Organisation News & Press Publications Legal Contact ESS
  • Science & Instruments
    Science Using Neutrons Instruments Data Management & Software Centre Labs and Sample Environment Committees For Users ESS Scientists Science Events Highlights of Published Papers
  • Technology
    Accelerator Target Controls
  • Building ESS
    The Building Project Progress reports from the ESS site Aerial Views
  • Partnerships
    In-Kind Contributions Doing business with ESS Grants
  • Careers
    Vacancies Living & Working in Scandinavia ESS Family Support

Secondary navigation

  • Publications Portal
  • Contact
  • Press
  • Behind ESS
Home

Main navigation

  • About ESS
    ess long pulse slide
    The ESS Mandate
    organisation
    ESS Organisation
    News and Press
    News & Press
    alt
    Publications
    legal and ip
    Legal
    contact ess
    Contact ESS
  • Science & Instruments
    Science using neutrons
    Science Using Neutrons
    instruments
    Instruments
    dmsc
    Data Management & Software Centre
    sss magnet
    Labs and Sample Environment
    Inauguration
    Committees
    Lab Kat
    For Users
    Scientist at work
    ESS Scientists
    diffraction
    Science Events
    Science papers image
    Highlights of Published Papers
  • Technology
    ess accelerator
    Accelerator
    target monolith
    Target
    ess ics
    Controls
  • Building ESS
    Building project
    The Building Project
    weekly construction updates
    Progress reports from the ESS site
    ess aerial snow
    Aerial Views
  • Partnerships
    tartu pump probe
    In-Kind Contributions
    procurement
    Doing business with ESS
    partner day
    Grants
  • Careers
    careers
    Vacancies
    scandinavia
    Living & Working in Scandinavia
    family
    ESS Family Support

13 September 2021

Accelerator

Normal Conducting Linac

Installation of the first Drift Tube Linac tank continues in the Normal Conducting Linac (NCL). The Faraday Cup and associated shielding blocks have been delivered to the tunnel and installation is under way.

Reinstallation of the adjusted temporary shielding wall separating the NCL from the rest of the tunnel, is about to start and the wall will be closed again by the end of September. This will enable continued installations in the superconducting linac whilst beam commissioning starts in the NCL.

Preparations and local tests for beam commissioning are ongoing in already installed components: the ion source, low energy beam transport (LEBT), radio-frequency quadrupole (RFQ) and medium energy beam transport (MEBT).

A safety readiness review was held last week.

Klystron Gallery

RF power tests continue for the Drift Tube Linac waveguide system, klystrons and modulators in the normal conducting gallery.

Low power tests of klystrons in the first medium beta RF ell are almost complete. A team of engineers and technicians from ESS Polish in-kind partner IFJ PAN conducts these tests, in close collaboration with ESS.

Further up in the gallery, in the medium and high beta sections, cable pulling and terminations, as well as rack fit-outs continue.

Cryomodules in Test Stand 2

Cold operation of the first medium beta cryomodule inside the test stand 2 bunker continues. The next serial-produced cryomodule is being prepared in the inspection area and the prototype cryomodule will be subject to transport tests to the accelerator tunnel shortly.

Target

Active Cells

Installation of floor valves continue.

The lower intrabay door is in place between the process and maintenance cells, and has been subject to power tests. Installation of the upper intrabay folding door follows.

Target Utility

Installations continue in the Utility block adjacent to the Monolith building. Cooling tanks have been delivered and placed on concrete foundations.

Target Monolith

The first boxes of port tubes, to be welded to the Monolith vacuum vessel, have arrived on site and are currently stored up on the high bay. Lifting tests will be conducted over the next couple of weeks, and welding works are planned to start in October.

Target roof and facades

The mounting of panels for the curved roof continue in the west end of the Target building, above the Target Entrance to D08 lab area as well as the roof over Transport Hall.

Façade cladding is still ongoing for the remaining parts of the A2T front, with a view to be completed by the end of September.

Experimental Halls & Labs

ESS has started the installation of lower shielding blocks for beamlines W3 and W4 (CSPEC and BIFROST) inside Experimental Hall 2.

The bunker crane runway in Experimental Hall 2 is currently subject to reinforcement works. Scaffolding is in place on the other side of the Monolith inside Experimental Hall 1 for the same works to follow there.

All NSS fume hoods for labs D04 and D08 are fully installed. Skanska is now in progress with final internal touch up works.

Part two of the Beamline Gallery is subject to sectional handover to ESS on Monday 13 September.

Central Utility Building

This week four heat exchangers were delivered to the Central Utility Building H01. These machines will be used for the surplus heat from ESS processes and be able to reheat water and recycle heat via a direct connection to the district heating network. Three more heat exchangers, weighing 4.5 tonnes each, will be delivered in the next couple of weeks. Connection to existing piping is next.

This installation is a key part of the surplus heat recycling system installed in the Central Utility Building, which will be operational from next summer. The system is provided and operated by ESS commercial partner E.ON.

Siteplan Archive
G01 NCL DTL1

Installation of Drift Tube Linac tank 1 under way in the ESS linac.

G01 DTL faraday cup

Faraday cup and shielding under installation by the drift tube linac.

G01 view through TSW

View through the temporary wall, separating the normal conducting linac from the superconducting linac.

G01 NCL DTL MEBT

Preparing for beam commissioning – this is the MEBT section.

G02 IFJ PAN klystron testing cell

Medium beta klystrons subject to power tests in the Klystron Gallery.

D02 AC floor valves

Installation of floor valves, from high bay to the Active Cells.

D02 Monolith high bay

View over Target high bay, where boxes of port tubes have arrived.

D02 TE to D08 sombrero

Cantilever roof cladding ongoing above the D08 lab building.

D02 TH sombrero

Installation of cladding panels above the Transport Hall.

D03 BIFROST support blocks

Mounting of lower support blocks for BIFROST beamline, inside Experimental Hall 2.

D03 view to beamline gallery

Beamline Gallery – construction completed and handover to ESS scheduled for 13 September.

D03 west bunker support blocks

Lower support blocks installation by the west sector bunker wall in Experimental Hall 2.

EON heat exchanger no 2 going in

Heat exchangers delivered for the surplus heat recycling system in the Central Utility Building.