Skip to main content

Main navigation

  • About ESS
    • The ESS Mandate
      • The ESS Story
    • ESS Organisation
      • Governance
        • Council Meetings
      • Committees
    • News & Press
      • Media Bank
      • Web Articles
    • Publications
    • Legal
      • ESS Privacy and Cookies Policies
    • Contact ESS
  • Science & Instruments
    • Science Using Neutrons
      • Chemistry of Materials, Magnetic & Electronic Phenomena
      • Engineering Materials, Geosciences, Archeology & Heritage Conservation and Fast Neutron Applications
      • Life Science & Soft Condensed Matter
      • Particle Physics
      • Future Science: What will we see at ESS?
        • Safer, lighter and stronger engineering materials
        • Fine-tuning 3D printing for space exploration
        • New tools in the fight against air pollution and global warming
        • Exploring the powerhouse of life
        • Better superconductors to improve cancer diagnosis
        • Bringing the most effective cancer drugs to market sooner
        • Lighting the way to next generation solar energy
        • New battery materials for a renewable energy future
        • Delivering on the Promise of Big Data
        • Putting a finger on the disorder essential to life
        • Unlocking the secrets of water
    • Instruments
      • BEER
      • BIFROST
      • CSPEC
      • DREAM
      • ESTIA
      • FREIA
      • HEIMDAL
      • LOKI
      • MAGIC
      • MIRACLES
      • NMX
      • ODIN
      • SKADI
      • T-REX
      • VESPA
    • Data Management & Software Centre
      • Computing Centre
    • Labs and Sample Environment
      • PREMP
      • FLUCO
      • TEFI
      • DEMAX
      • SULF
      • MESI
    • Committees
    • For Users
    • ESS Scientists
    • Science Events
    • Highlights of Published Papers
  • Technology
    • Accelerator
      • How It Works
      • LINAC
      • Beam Physics & Beam Diagnostics
      • Cryogenics
      • Vacuum
      • Radio Frequency Systems
      • Accelerator Test Stands
    • Target
      • How the Target works
    • Controls
  • Building ESS
    • The Building Project
      • Site, Architecture & Sustainability
      • Licensing & Planning
      • Radiation Protection & Safety
    • Progress reports from the ESS site
    • Aerial Views
  • Partnerships
    • In-Kind Contributions
    • Doing business with ESS
      • Supplier Information
      • Procurement Listings
      • Contract Award Notices
    • Grants
      • ESS in the HALRIC Project
  • Careers
    • Vacancies
    • Living & Working in Scandinavia
      • In Sweden
      • In Denmark
    • ESS Family Support
Webmail
ESS Inside
  • About ESS
    The ESS Mandate ESS Organisation News & Press Publications Legal Contact ESS
  • Science & Instruments
    Science Using Neutrons Instruments Data Management & Software Centre Labs and Sample Environment Committees For Users ESS Scientists Science Events Highlights of Published Papers
  • Technology
    Accelerator Target Controls
  • Building ESS
    The Building Project Progress reports from the ESS site Aerial Views
  • Partnerships
    In-Kind Contributions Doing business with ESS Grants
  • Careers
    Vacancies Living & Working in Scandinavia ESS Family Support

Secondary navigation

  • Publications Portal
  • Contact
  • Press
  • Behind ESS
Home

Main navigation

  • About ESS
    ess long pulse slide
    The ESS Mandate
    organisation
    ESS Organisation
    News and Press
    News & Press
    alt
    Publications
    legal and ip
    Legal
    contact ess
    Contact ESS
  • Science & Instruments
    Science using neutrons
    Science Using Neutrons
    instruments
    Instruments
    dmsc
    Data Management & Software Centre
    sss magnet
    Labs and Sample Environment
    Inauguration
    Committees
    Lab Kat
    For Users
    Scientist at work
    ESS Scientists
    diffraction
    Science Events
    Science papers image
    Highlights of Published Papers
  • Technology
    ess accelerator
    Accelerator
    target monolith
    Target
    ess ics
    Controls
  • Building ESS
    Building project
    The Building Project
    weekly construction updates
    Progress reports from the ESS site
    ess aerial snow
    Aerial Views
  • Partnerships
    tartu pump probe
    In-Kind Contributions
    procurement
    Doing business with ESS
    partner day
    Grants
  • Careers
    careers
    Vacancies
    scandinavia
    Living & Working in Scandinavia
    family
    ESS Family Support

15 November 2021

Accelerator

Beam on!

Beam commissioning is now ongoing – beam has successfully been extracted from the ion source to the first faraday cup.

This phase of beam commissioning, where the goal is to extract and send beam through the Low Energy Beam Transport, the Radio-Frequency Quadrupole and finally the Medium Energy Beam Transport, will go on for some time. It will test the functionality of all systems installed working together in harmony.

Cryomodule testing

The medium beta cryomodule inside the test stand bunker has been subject to warm up, in preparation for the exchange of a vacuum gauge next week. The full test cycle for this cryomodule will then be completed, before swapping to the next cryomodule in line.

Target

Target cantilever roof

The ESS sombrero is structurally completed. A final inspection revealed a few areas that need touch up and adjustment, which will be actioned now.

Cryogenic Moderator System (CMS) in place

The Cryogenic Moderator System, brought to ESS by German in-kind partner Jülich, was successfully lifted to a hydrogen room on the top floor of the A2T building.

The main function of the CMS is to provide liquid hydrogen for the cold neutron production in the Target moderators. The cold hydrogen slows down the fast thermal neutrons released from the Target, to a speed suitable for the instruments.

Target Monolith

Welding of port tubes and the NN bar to the Monolith vessel continues.

Experimental Halls

LOKI and FREIA

Precast concrete and stairs are in place for the LOKI and FREIA hutches. Platforms and bridges are yet to be installed, and the concrete will be painted in white.

The base plate installation continues for the LOKI beamline and cave. The detector vessel will be moved in position in just a few weeks’ time.

Experimental Halls 1 & 2

The bunker crane runway reinforcement works are now completed inside Experimental Hall 1 and the scaffolding has been taken down.  The bunker cranes are subject to redesign at the manufacturer in Norway and will be reinstalled soon.

Siteplan Archive
D02 Monolith

The Monolith vessel, port tubes and NN bar, as seen from high bay level.

B01 office

ESS office, viewed from the Target building roof.

D01 bunker

Neutron shielding bunker and crane in Experimental Hall 1.

D02 sombrero landscape

The cantilever roof surrounding the Target building and two short instrument halls is structurally completed.

G02 TS2 cryomodules

Test stand for medium beta cryomodules.

G01 FEB PAS blue light

Blue light in the tunnel, indicating BEAM ON, is visible from outside the access station in the front end building.

D03 hall hutch

Control hutches for instruments LOKI and FREIA are under construction inside Experimental Hall 2.

D03 LoKI base plates

The outline for the LOKI scientific cave, where the detector vessel will be placed.

A2T hydrogen room  moving in CMS

Cryogenic Moderator System box lifted to the top level of the Target building.

CMS lift-3

Lift from ground level of big box containing the moderator cryostat.