Skip to main content

Main navigation

  • About ESS
    • The ESS Mandate
      • The ESS Story
    • ESS Organisation
      • Governance
        • Council Meetings
      • Committees
    • News & Press
      • Media Bank
      • Web Articles
    • Publications
    • Legal
      • ESS Privacy and Cookies Policies
    • Contact ESS
  • Science & Instruments
    • Science Using Neutrons
      • Chemistry of Materials, Magnetic & Electronic Phenomena
      • Engineering Materials, Geosciences, Archeology & Heritage Conservation and Fast Neutron Applications
      • Life Science & Soft Condensed Matter
      • Particle Physics
      • Future Science: What will we see at ESS?
        • Safer, lighter and stronger engineering materials
        • Fine-tuning 3D printing for space exploration
        • New tools in the fight against air pollution and global warming
        • Exploring the powerhouse of life
        • Better superconductors to improve cancer diagnosis
        • Bringing the most effective cancer drugs to market sooner
        • Lighting the way to next generation solar energy
        • New battery materials for a renewable energy future
        • Delivering on the Promise of Big Data
        • Putting a finger on the disorder essential to life
        • Unlocking the secrets of water
    • Instruments
      • BEER
      • BIFROST
      • CSPEC
      • DREAM
      • ESTIA
      • FREIA
      • HEIMDAL
      • LOKI
      • MAGIC
      • MIRACLES
      • NMX
      • ODIN
      • SKADI
      • T-REX
      • VESPA
    • Data Management & Software Centre
      • Computing Centre
    • Labs and Sample Environment
      • PREMP
      • FLUCO
      • TEFI
      • DEMAX
      • SULF
      • MESI
    • Committees
    • For Users
    • ESS Scientists
    • Science Events
    • Highlights of Published Papers
  • Technology
    • Accelerator
      • How It Works
      • LINAC
      • Beam Physics & Beam Diagnostics
      • Cryogenics
      • Vacuum
      • Radio Frequency Systems
      • Accelerator Test Stands
    • Target
      • How the Target works
    • Controls
  • Building ESS
    • The Building Project
      • Site, Architecture & Sustainability
      • Licensing & Planning
      • Radiation Protection & Safety
    • Progress reports from the ESS site
    • Aerial Views
  • Partnerships
    • In-Kind Contributions
    • Doing business with ESS
      • Supplier Information
      • Procurement Listings
      • Contract Award Notices
    • Grants
      • ESS in the HALRIC Project
  • Careers
    • Vacancies
    • Living & Working in Scandinavia
      • In Sweden
      • In Denmark
    • ESS Family Support
Webmail
ESS Inside
  • About ESS
    The ESS Mandate ESS Organisation News & Press Publications Legal Contact ESS
  • Science & Instruments
    Science Using Neutrons Instruments Data Management & Software Centre Labs and Sample Environment Committees For Users ESS Scientists Science Events Highlights of Published Papers
  • Technology
    Accelerator Target Controls
  • Building ESS
    The Building Project Progress reports from the ESS site Aerial Views
  • Partnerships
    In-Kind Contributions Doing business with ESS Grants
  • Careers
    Vacancies Living & Working in Scandinavia ESS Family Support

Secondary navigation

  • Publications Portal
  • Contact
  • Press
  • Behind ESS
Home

Main navigation

  • About ESS
    ess long pulse slide
    The ESS Mandate
    organisation
    ESS Organisation
    News and Press
    News & Press
    alt
    Publications
    legal and ip
    Legal
    contact ess
    Contact ESS
  • Science & Instruments
    Science using neutrons
    Science Using Neutrons
    instruments
    Instruments
    dmsc
    Data Management & Software Centre
    sss magnet
    Labs and Sample Environment
    Inauguration
    Committees
    Lab Kat
    For Users
    Scientist at work
    ESS Scientists
    diffraction
    Science Events
    Science papers image
    Highlights of Published Papers
  • Technology
    ess accelerator
    Accelerator
    target monolith
    Target
    ess ics
    Controls
  • Building ESS
    Building project
    The Building Project
    weekly construction updates
    Progress reports from the ESS site
    ess aerial snow
    Aerial Views
  • Partnerships
    tartu pump probe
    In-Kind Contributions
    procurement
    Doing business with ESS
    partner day
    Grants
  • Careers
    careers
    Vacancies
    scandinavia
    Living & Working in Scandinavia
    family
    ESS Family Support

14 September 2020

Target

A concrete top coat (screed) has been applied on all three levels of the Target Entrance Building, and metal frameworks for gypsum walls are being fitted. Interior works will be ongoing throughout the autumn, and parallel installation works (piping, cabling, ventilation, etc.) will begin in October. Meanwhile externally, installation of a curtain wall is ongoing and roof works are progressing,

In the Monolith and Utility High Bay, floors have been treated with epoxy and are now covered with protective boards. The section of the High Bay closest to the Accelerator to Target (A2T) will be done once the A2T roof is completed. Installation of the High Bay overhead crane, which is expected to be operational by the end of October, is ongoing.

The steel superstructure is now in place for the A2T, and installation of sandwich panels is ongoing. Inside the building, painting is underway, and epoxy treatment will follow later this month. The A2T ventilation stack, measuring 32 metres (15 metres of which will protrude from the roof), will be installed shortly.

Installation of the steel frame and hollow-core slabs for the entrance area of the Transport Hall have been completed, with reinforcement for screed to follow. Columns have been painted and a primer applied to the floor inside the Transport Hall, where the overhead crane is now operational. ESS will gain parallel access this week in order to start the installation of a mock-up area. At the same time, conventional installation works will be ongoing.

Testing and commissioning of a Target Substation are in the final stages, meaning it will be ready for handover to ESS at the end of October.

Experiment Halls

Construction of a scientific cave for the BIFROST instrument is in progress inside Experimental Hall 3, with the third layer walls having recently been cast. A team of UK lab fitters have been able to return to Lund to complete the lab installations in the adjacent laboratories. An estimated eight weeks' work remains before the labs can be subject to testing and commissioning prior to operation. Meanwhile, electrical Infrastructure works are ongoing, which involve electrical power and network infrastructure installations in all experiment buildings. Raceway supports and cable trays are currently being mounted.

A Neutron Beam Optics Assembly (NBOA)  integration tent is being equipped in the east corner of the large, curved hall. NBOA is the first physical part of each instrument and the neutron guide section just next to the moderator, closest to the target wheel. The NBOA is connected to a Neutron Beam Port Insert (NBPI), which is a steel plug that will be inserted into the beam port for each instrument inside the Monolith. The temporary tent structure consists of separated areas with different environmental requirements, and will be used to test, align and prepare components before installation in the Monolith area.

The steel structure for the section connecting part 1 to part 2 of the Beam Line Gallery is progressing. The so-called seismic frame closest to the Beam Line wall by Experimental Hall 2 is already completed.

The metal roof for Experiment Hall 1 has been completed over the bunker area, with the roof membrane to follow. Installation of the remaining roof trusses at the end nearest the A2T will start this week. At the same time, the curved cantilever roof is being fitted along the façade. Meanwhile, in Experimental Hall 2, installation of permanent light fittings is ongoing, and the first cable ladders are being fitted on the north wall.

Preparations are ongoing to start the next phase of the shielding bunker installation, as ESS gains parallel access to the Hall 2 side of the bunker area surrounding the Monolith later this month. A steel structure outlining the bunker will be mounted, while the installation, testing and commissioning of the bunker crane continues. Installation of concrete blocks for the bunker is set to begin by the end of October. The bunker crane, which by then will be operational to perform heavy lifts, will be  used for this task.