Skip to main content

Main navigation

  • About ESS
    • The ESS Mandate
      • The ESS Story
    • ESS Organisation
      • Governance
        • Council Meetings
      • Committees
    • News & Press
      • Media Bank
      • Web Articles
    • Publications
    • Legal
      • ESS Privacy and Cookies Policies
    • Contact ESS
  • Science & Instruments
    • Science Using Neutrons
      • Chemistry of Materials, Magnetic & Electronic Phenomena
      • Engineering Materials, Geosciences, Archeology & Heritage Conservation and Fast Neutron Applications
      • Life Science & Soft Condensed Matter
      • Particle Physics
      • Future Science: What will we see at ESS?
        • Safer, lighter and stronger engineering materials
        • Fine-tuning 3D printing for space exploration
        • New tools in the fight against air pollution and global warming
        • Exploring the powerhouse of life
        • Better superconductors to improve cancer diagnosis
        • Bringing the most effective cancer drugs to market sooner
        • Lighting the way to next generation solar energy
        • New battery materials for a renewable energy future
        • Delivering on the Promise of Big Data
        • Putting a finger on the disorder essential to life
        • Unlocking the secrets of water
    • Instruments
      • BEER
      • BIFROST
      • CSPEC
      • DREAM
      • ESTIA
      • FREIA
      • HEIMDAL
      • LOKI
      • MAGIC
      • MIRACLES
      • NMX
      • ODIN
      • SKADI
      • T-REX
      • VESPA
    • Data Management & Software Centre
      • Computing Centre
    • Labs and Sample Environment
      • PREMP
      • FLUCO
      • TEFI
      • DEMAX
      • SULF
      • MESI
    • Committees
    • For Users
    • ESS Scientists
    • Science Events
    • Highlights of Published Papers
  • Technology
    • Accelerator
      • How It Works
      • LINAC
      • Beam Physics & Beam Diagnostics
      • Cryogenics
      • Vacuum
      • Radio Frequency Systems
      • Accelerator Test Stands
    • Target
      • How the Target works
    • Controls
  • Building ESS
    • The Building Project
      • Site, Architecture & Sustainability
      • Licensing & Planning
      • Radiation Protection & Safety
    • Progress reports from the ESS site
    • Aerial Views
  • Partnerships
    • In-Kind Contributions
    • Doing business with ESS
      • Supplier Information
      • Procurement Listings
      • Contract Award Notices
    • Grants
      • ESS in the HALRIC Project
  • Careers
    • Vacancies
    • Living & Working in Scandinavia
      • In Sweden
      • In Denmark
    • ESS Family Support
Webmail
ESS Inside
  • About ESS
    The ESS Mandate ESS Organisation News & Press Publications Legal Contact ESS
  • Science & Instruments
    Science Using Neutrons Instruments Data Management & Software Centre Labs and Sample Environment Committees For Users ESS Scientists Science Events Highlights of Published Papers
  • Technology
    Accelerator Target Controls
  • Building ESS
    The Building Project Progress reports from the ESS site Aerial Views
  • Partnerships
    In-Kind Contributions Doing business with ESS Grants
  • Careers
    Vacancies Living & Working in Scandinavia ESS Family Support

Secondary navigation

  • Publications Portal
  • Contact
  • Press
  • Behind ESS
Home

Main navigation

  • About ESS
    ess long pulse slide
    The ESS Mandate
    organisation
    ESS Organisation
    News and Press
    News & Press
    alt
    Publications
    legal and ip
    Legal
    contact ess
    Contact ESS
  • Science & Instruments
    Science using neutrons
    Science Using Neutrons
    instruments
    Instruments
    dmsc
    Data Management & Software Centre
    sss magnet
    Labs and Sample Environment
    Inauguration
    Committees
    Lab Kat
    For Users
    Scientist at work
    ESS Scientists
    diffraction
    Science Events
    Science papers image
    Highlights of Published Papers
  • Technology
    ess accelerator
    Accelerator
    target monolith
    Target
    ess ics
    Controls
  • Building ESS
    Building project
    The Building Project
    weekly construction updates
    Progress reports from the ESS site
    ess aerial snow
    Aerial Views
  • Partnerships
    tartu pump probe
    In-Kind Contributions
    procurement
    Doing business with ESS
    partner day
    Grants
  • Careers
    careers
    Vacancies
    scandinavia
    Living & Working in Scandinavia
    family
    ESS Family Support

29 June 2020

Target

The construction of the NMX cave is nearing completion, as the overhead internal crane is in place and fitting of  roof elements is ongoing. Preparation has now started for the next cave to be built - the one for the instrument BIFROST - and erection of the cave structure is set to start in August.

The very first steel columns for part 2 of the Beamline Gallery building were put in place last week, and roof truss no 12 has been fitted for  Experimental Hall 1.

The steel for the Transport Hall entrance area is nearing completion, and sandwich panels have been fitted to the south corridor of the Technical Galleries.

Fitting of the R6 bunker system on the south side of the Monolith is ongoing, with a curved beam and 22 pillars. On the Experimental Hall 2 side, where the R6 system is already in place, preparations have started for bunker crane installation, and an overhead crane has been mounted in the Transport Hall.

Internal seals and  profiles are being installed  on the Active Cell-side of the high bay, and a connecting cell steel door, weighting 14 tonnes, has been fitted between Tom’s Room and the Monolith area.

Accelerator

A Machine Access System (MAS) and a Personnel Access System (PAS) are being installed n the basement of Front End Building. These are part of the protection system for the accelerator tunnel and will be a means to control access to the Linac, once it goes into commissioning. Similar equipment (PAS) will be installed in the HEBT Loading Bay area (level 090) and in the Target, as well as in the experiment halls. For the commissioning of the Normal Conducting Linac, the Temporary Shielding Wall being built will be used for radiation protection/access.

General

The team at the Waste Treatment Facility are aiming to have the roof works completed before the summer holiday period. Hollow core slabs are in place for the central hall and TRP (Tremco Roof Preservative) roofing has been installed on both sides, and insulation and a roof membrane is to be fitted on top.

The office building atrium on Campus is really starting to take shape,  with its wooden panels and 'Hogwarts' like stairs.

This is the last Construction Update for a while - see you after the summer!